Lagos airport road project nears 75% completion

By Victor Gbonegun
11 March 2019   |   2:56 am
The contractor handling reconstruction of Oshodi-Murtala Muhammed International Airport Road, Messrs Hi-tech Construction Company, has disclosed that the six kilometres project is about 75per cent completion, assuring residents of quality job.

Chairman, Nigerian Society of Engineers (NSE), Ikeja branch, Mrs. Olufunmilade  Akingbagbohun; Deputy Director, Projects, Lagos Ministry of Works and Infrastructure, Bashiru Adewale; Project Manager, Hitech Construction Company,Mrs. Abiola Kosegbe; Resident Engineer, Murtala Muhammed International Airport (MMIA), Mr. Sachin Ramsunder; General Manager. Lagos State Material Testing Laboratory, Mrs. Ronke Olukoko; Past chairman, NSE, Ikeja branch, Olalekan Ajani and Mr. Charles Akintola during an industrial visit to the ongoing construction works at the Murtala Muhammed International Airport road in Lagos.

The contractor handling reconstruction of Oshodi-Murtala Muhammed International Airport Road, Messrs Hi-tech Construction Company, has disclosed that the six kilometres project is about 75per cent completion, assuring residents of quality job.

The Project Manager, Sachi Ramsunder, who spoke during a technical visit by members of the Nigerian Society of Engineers (NSE), Ikeja Branch, explained that with enough commitments, the bulk of work remaining for the fly over bridge and the road network would be completed in about five weeks time.

The Oshodi-International Airport Road expansion project is designed as a 10-lane highway comprising, three express lanes and two-service lanes in each direction. It will also accommodate five pedestrian bridges, one U-turn and flyover bridges as well as walkways, among others.

The reconstruction is expected to end gridlocks and scale-up value of property in the area. Lagos State government had promised to deliver the Airport Road in 15 months following its upgrade from four to ten lanes. Work on the project commenced on September 2017 and is to be delivered by May 2019.He said with the quality of construction equipment and materials mobilized for the road, it would be constructed to meet international standard.

The project manager told the engineers that the firm’s newly acquired ‘Wirtgen WR 250 Recycler’ for the project is capable of delivering 12,000 square metres performance maximum daily, adding that the “machine can mix two per cent bitumen, one per cent cement, 50 per cent stone base and 50 per cent reclaimed existing asphalt with water which makes road construction with the machine faster and better with a higher quality.

Expounding on the visit, NSE chairman, Ikeja branch, Olufunmilade Akingbagbohun said the association seeks to ensure that there is quality in terms of materials and machines used for the road project and the general infrastructural development in Lagos State.

“We appreciate what the state government is doing through the ministry of works and infrastructure and we have come to conduct an inspection of the site, look at quality control that has been put in place, the quality of materials and the machines and endorse the function of the road. From what we have seen, there is improvement on work done, on the project”.

He lauded the involvement of about 50per cent local engineers working on the project through the construction firm and the ministry of works and infrastructure describing it as an acknowledgment of local content in Nigerian construction sector.

Also speaking during the visit, Deputy Director, Ministry of Works and infrastructure, Lagos state, Mrs. Abiola Kosegbe who represented the Commissioner for the ministry, Ade Akinsanya declared that project is on target for the slated delivery date. According to her, all the site engineers are working toward the schedule designed for the project.She appealed to motorists plying the road to endure the inconveniences caused by the massive project, stressing that it would pay off when it’s completed.